Introduction
Question One
What is it we do that's valuable?
A Value Stream
Types of Value Streams
Value Stream Tasks
A Value Stream in Detail
Value Stream Statistics
- 35 different activities
- 43 days lead time
- 7 days touch time
Question Two
Why does it take so long?
Single Task Analysis - Data
% Busy |
Wait Time |
0% |
0 |
50% |
1 |
75% |
3 |
90% |
9 |
95% |
19 |
99% |
99 |
Single Task Analysis - Graph
*Graph from the The Phoenix Project, by Gene Kim, Kevin Behr and George Spafford
Little's Law
L = λW
W = L/λ
Linked Queues
Question Three
What alternatives are there?
An Alternative Value Stream
Value Stream Statistics
- 13 different activities
- 5 days lead time
- 4 days touch time
Comparison of Value Streams
Resource Optimisation vs Flow Optimisation
- 43 days lead time
- 7 days touch time
- 5 days lead time
- 4 days touch time
Product Economic Framework
Standard economic measure:
Life-Cycle Profits
Cost of Delay
What happens to life-cycle profits if release is delayed 7 weeks?
References
- Lean Lego - The Red Brick Cancer, by HÃ¥kan Forss
- Principles of Product Development Flow, by Donald G. Reinersten
- The Phoenix Project, by Gene Kim, Kevin Behr and George Spafford
- Slack: Getting Past Burnout, Busywork, and the Myth of Total Efficiency, by Tom DeMarco
- The Toyota Way, by Jeffrey K. Liker
- Value Stream Mapping, by Mike Rother
- Specification by Example, by Gojko Adzic
Joe Schmetzer • @tumbarumba